Raised Access Floors in Irish Offices — Lift a Panel Before You Tender

6 days ago
3 min read

An office fit-out can lose a usable raised access floor one floor box at a time. The furniture plan shifts, the old openings land in aisles or beneath chair castors, and the strip-out drawing still says “remove floor throughout”. Lift representative panels before tender, then draw the new furniture, partitions and services over the existing panel grid. The overlay will show where a small layout change could save an entire run of panels.

A raised access floor is a system of removable panels supported above the structural slab. The void can carry power and data and, in some buildings, distribute air. Reuse depends on the condition and performance of the assembly and on what the new office will ask it to do.

Installer kneeling beside an open square in a raised access floor, with adjoining white panels and exposed supports.

Raised access floor installation at the future Long Island Rail Road passenger concourse in New York. Photograph by MTA Capital Construction Mega Projects, CC BY 2.0. Display crops used for previews.

What Sisk kept at Citywest

When Sisk opened its retrofitted headquarters at Citywest Business Campus in June 2024, the fit-out reused raised access floors alongside carpet tiles, ceiling tiles and external paving. Sisk reported a 17% reduction against an all-new fit-out scenario for those reuse measures together. The published case study gives no separate figure for flooring. Sisk’s Citywest retrofit

For a tender in Ireland, the EPA’s green public procurement criteria for office buildings provide a starting point. They call for a strip-out or pre-demolition audit that itemises materials and assesses recovery potential, including flooring. An overlay takes that inventory one step further. It gives each viable area of floor a place in the proposed layout and a corresponding item in the pricing schedule. EPA office building procurement criteria, section C

What to check when you lift the panels

Survey representative open-plan areas as well as places where conditions change, such as the core, former meeting rooms and kitchen edges. Record the panel and support system, the floor box positions, and any damage, movement or gaps. Agree with the flooring specialist how to verify suitability for the proposed loads, including concentrated loads from storage, joinery and other heavy items.

Ask the services engineer what each part of the void does. Where the floor serves as a supply-air plenum, agree how the proposed panel and seal arrangement will be checked for leakage. Check partitions and penetrations with the fire and acoustic designers. Mace and Arup’s study of material reuse flags airtightness as a constraint for reclaimed floor panels. Mace and Arup, Optimising Circularity in the Built Environment, p. 34

Then overlay desks, floor boxes, partitions and the routes for accessing services. Mark the boxes you can keep, those that can move with interchangeable panels, and those that need new openings. Confirm compatibility with the complete floor system before assuming a panel can move between zones. Give facilities staff a way to lift the panels they will need once furniture and joinery are installed.

A worked example on a 720 m² office floor

In this illustrative scenario, a survey finds 540 m² fit to retain in place, 108 m² that needs local work, and 72 m² requiring replacement. That is 75%, 15% and 10% of the surveyed floor area. In the middle category, 36 m² is affected solely by the proposed position of desk power. The balance needs work for other reasons, such as worn panels or changes at partition lines.

The architect and services engineer move two desk runs to use existing floor boxes, after checking circulation and cable reach. Those 36 m² move into the retain-in-place column. The tender now carries 576 m² retained in place (80%), 72 m² for local works (10%) and 72 m² for replacement (10%). Within local works, price panel swapping, support adjustments and new cut-outs as separate items where applicable. At handover, update the figures from the installed condition.

The 80% measures floor area left in place. A carbon comparison would need its own scope and evidence, including the replacement products avoided and the materials, transport and works required for the reuse option.

Five checks to put in the tender

1. Which zones stay in place, and what has the survey established about condition and suitability?

2. Which desk runs and floor boxes can use the existing grid without losing circulation or maintenance access?

3. What performance evidence is required for changes to panels, supports, seals and penetrations?

4. Who protects the retained floor during strip-out, and how will damaged panels and latent defects be priced?

5. Which drawings, quantities and compatible spares will be handed over to facilities management?

Put the coloured overlay in the tender pack beside the furniture and services plans. A contractor can then see where to protect the existing floor, where to price work and where the quantities depend on opening up.

 
 
 