Office Furniture Reuse in Ireland — What Should Architects Count?
A Dublin office starts with 100 chairs and finishes with 80. The project team keeps 60, sends 25 to another workplace and buys 15 new. On handover day, the client asks how much furniture the fit-out reused. Three different percentages describe what happened, and each tells the client something different.
To measure office furniture reuse, keep two records. Start with an inventory of the furniture you inherited and track where it went. Then use the installed furniture schedule to record where the finished office’s furniture came from. Both records belong in the architect’s handover pack.
Three numbers that answer different questions
Retained on site. Divide the number of existing items that returned to use on the project by the number recorded at the start. Count furniture kept in place, relocated within the project or refurbished and returned to service.
Reused elsewhere. Divide the number of existing items with a confirmed destination for reuse by the same opening inventory. Record items awaiting a recipient separately until the transfer and intended use are confirmed.
Installed pre-owned. Divide the number of pre-owned items in the completed fit-out by the total installed quantity. Include both items retained by the project and used items brought in from elsewhere.
Set the project boundary and count by furniture type. Sixty task chairs and one large meeting table are 61 assets, but the aggregate gives very little guidance on what to buy or repair. Keep separate lines for task chairs, workstations, meeting tables and storage. Define the counting unit for modular items before the audit.
A worked chair schedule for a Dublin office
The opening audit records 100 chairs. Forty-eight go straight back into service and 12 return after refurbishment, giving 60 retained chairs. Another workplace accepts 25 for reuse. The remaining 15 go to material recovery. The new plan needs 80 chairs, so the project installs the 60 retained chairs, five pre-owned chairs sourced externally and 15 new ones.
At handover the figures are 60% retained on site (60/100), 25% reused elsewhere (25/100) and 81% of installed chairs pre-owned (65/80, rounded). The first two percentages describe the fate of the original stock. The third describes the mix in the completed workplace. Keep the fractions beside the percentages so a reader can reconstruct the claim.

What the CNP Santander fit-out illustrates
At Hatch Street in Dublin 2, CNP Santander reduced its office footprint and reconfigured the space for workstations, cellular offices, meeting rooms and a staff canteen. Fit-out contractor Ardmac reports that the design team sought to reuse as much existing furniture, fixtures and equipment as possible. Ardmac’s published account gives no audited quantities, so the percentages above are illustrative. The case shows why a smaller floorplate needs two records. Some stock can serve the new layout, while another share may need a destination beyond it.

Ondarreta Bai swivel seating in a timber-lined meeting room. Furniture reference from the Ardagh Agencies gallery. View Ondarreta’s current Bai swivel specification.
How to build the measure into an Irish fit-out tender
Put the opening inventory in the tender pack before inviting prices for new furniture. Give each batch an ID, location, quantity, condition and proposed destination. Ask tenderers to price repair and refurbishment separately, with the work, transport, temporary storage, turnaround and quality checks visible. Inspect a trial batch before committing to the balance. Count only furniture that meets the brief for the intended use and is signed off for return to service.
Ireland’s Environmental Protection Agency suggests auditing existing stock before tendering for furniture refurbishment. Its green public procurement criteria also ask suppliers to describe the work, materials and quality controls behind the proposed refurbishment. Private commercial teams can borrow that verification approach when writing an interiors brief.
Assign an owner to every outgoing batch. Have facilities record stock at survey, the contractor record collections, and the project team reconcile what was installed against the schedule. If a charity, dealer or second site takes a batch, record the recipient and intended use. Where there is only a collection docket and no evidence of reuse, leave the outcome open in the register.
Does an 81% reuse rate mean 81% less embodied carbon?
An item count describes the furniture mix. A carbon assessment compares emissions across equivalent scenarios over a stated period. A prospective life-cycle study published in October 2026 modelled recurring fit-outs for an Auckland office and found the results particularly sensitive to furniture reuse assumptions and how efficiently the office space was designed. To make a carbon claim for an Irish project, compare options that provide the same function and account for repair materials, transport, expected service life and any replacements within the study period.
Five questions to take to the next design review
Which furniture was in scope on the survey date, and how did we count it?
Which items can meet the new brief as they are, and which need a trial repair?
Who will confirm where outgoing batches go and whether they return to use?
What share of the installed schedule is retained, sourced pre-owned or purchased new?
Can the client trace each handover figure back to an inventory or a signed-off schedule?
When the client asks how much was reused, bring both schedules to the table. The opening inventory shows how the team looked after the client’s existing assets. The installed schedule shows which purchases the new brief still required.
Read our guide to circular office fit-outs in Ireland or draw the furniture delivery route before moving or ordering bulky pieces.
Ardagh Agencies represents Ondarreta in Ireland. For furniture sizes, finishes and samples for an Irish commercial interiors project, see our office furniture for projects.